A manufacturing work order is modeled as a directed acyclic graph of operations with durations in days, and every path ends at one shipping node. Compute the total lead time as the critical path length from any starting operation to shipping. It tests graph modeling, dependency ordering and longest-path reasoning.

Work Order Lead Time: Critical Path Through an Operations DAG to Shipping

Company: Hadrian

Role: Software Engineer

Category: Coding & Algorithms

Difficulty: hard

Interview Round: Technical Screen

A manufacturing work order is modeled as a directed acyclic graph. Each node is an operation, such as machining or inspection, that takes a whole number of days. Each edge `(source, target)` is a dependency: operation `target` cannot start until operation `source` has finished. Every path ends at a single terminal node of type `"shipping"`. Operations that do not depend on each other can run at the same time, so the total lead time of the work order is its critical path length: the longest path from any starting node (a node with no incoming edges) to the shipping node. Return the lead time. ### Function Signature ```python def work_order_lead_time(nodes: list[tuple[str, str, int]], edges: list[tuple[str, str]]) -> int: ``` Each node is `(id, type, duration)`, with `duration` in days, and each edge is `(source, target)`. ### Rules - The length of a path is the sum of the durations of all nodes on it, including its first node and the shipping node. - A starting node is a node with no incoming edges. If the work order contains only the shipping node, that node alone forms the only path. - Return the maximum length over all paths that begin at a starting node and end at the shipping node. - Node types other than `"shipping"` do not affect the result. ### Constraints - `1 <= len(nodes) <= 10^4` - `0 <= len(edges) <= 5 * 10^4` - `0 <= duration <= 1000` for every node. - Node ids are unique, nonempty strings of at most 20 characters. Types are nonempty lowercase strings. - Exactly one node has type `"shipping"`, and it has no outgoing edges. - Every edge connects two different existing nodes, and no edge appears twice. - The graph has no cycles, and every node has a directed path to the shipping node. - The answer is at most `10^7`. ### Examples **Example 1** ```text Input: nodes = [("m1", "machining", 2), ("m2", "machining", 4), ("i1", "inspection", 1), ("m3", "machining", 3), ("i2", "inspection", 2), ("ship", "shipping", 0)] edges = [("m1", "i1"), ("m2", "i1"), ("i1", "m3"), ("i1", "i2"), ("m3", "ship"), ("i2", "ship"), ("m1", "i2")] Output: 8 ``` The starting nodes are `m1` and `m2`. The longest path is `m2 -> i1 -> m3 -> ship`, with length 4 + 1 + 3 + 0 = 8. The other paths are shorter: for example, `m1 -> i1 -> m3 -> ship` has length 6, `m2 -> i1 -> i2 -> ship` has length 7, and `m1 -> i2 -> ship` has length 4. **Example 2** ```text Input: nodes = [("x", "machining", 1), ("y", "machining", 1), ("z", "inspection", 1), ("w", "machining", 5), ("ship", "shipping", 1)] edges = [("x", "y"), ("y", "z"), ("z", "ship"), ("w", "ship")] Output: 6 ``` The chain `x -> y -> z -> ship` has more operations but length 4, while `w -> ship` has length 5 + 1 = 6. **Example 3** ```text Input: nodes = [("ship", "shipping", 2)], edges = [] Output: 2 ``` The shipping node is the only node, so the lead time is its own duration.

Overview: A manufacturing work order is modeled as a directed acyclic graph of operations with durations in days, and every path ends at one shipping node. Compute the total lead time as the critical path length from any starting operation to shipping. It tests graph modeling, dependency ordering and longest-path reasoning.

Read the full Hadrian Software Engineer interview experience this question came from

A manufacturing work order is modeled as a directed acyclic graph. Each node is an operation, such as machining or inspection, that takes a whole number of days. Each edge `(source, target)` is a dependency: operation `target` cannot start until operation `source` has finished. Every path ends at a single terminal node of type `"shipping"`. Operations that do not depend on each other can run at the same time, so the lead time of the work order is its critical path length: the longest path from any starting node (a node with no incoming edges) to the shipping node. Implement `work_order_lead_time(nodes, edges)` and return the lead time. Each node is `(id, type, duration)`, with `duration` in days, and each edge is `(source, target)`, where `source` and `target` are node ids. ### Rules - The length of a path is the sum of the durations of all nodes on it, including its first node and the shipping node. - A starting node is a node with no incoming edges. If the work order contains only the shipping node, that node alone forms the only path. - Return the maximum length over all paths that begin at a starting node and end at the shipping node. - Node types other than `"shipping"` do not affect the result. - Nodes and edges may be listed in any order. ### Input and output - Python: `nodes` is a list of `(id, type, duration)` tuples and `edges` is a list of `(source, target)` tuples. - JavaScript: each node is an array `[id, type, duration]` and each edge is an array `[source, target]`. - Java: `nodes` is a `java.util.List<java.util.List<Object>>`; each inner list holds `id` (a `String`), `type` (a `String`) and `duration` (a `Number`). `edges` is a `java.util.List<java.util.List<String>>` whose inner lists hold `source` and `target`. - C++: `nodes` is a `std::vector<std::tuple<std::string, std::string, int>>` and `edges` is a `std::vector<std::vector<std::string>>` whose inner vectors hold `source` and `target`. - Return one integer, the lead time. The answer is at most 10^7, so it never exceeds 2^31 - 1 and fits in a 32-bit `int` in Java and C++. ### Constraints - `1 <= len(nodes) <= 10^4` - `0 <= len(edges) <= 5 * 10^4` - `0 <= duration <= 1000` for every node. - Node ids are unique, nonempty strings of at most 20 characters. Types are nonempty lowercase strings. - Exactly one node has type `"shipping"`, and it has no outgoing edges. - Every edge connects two different existing nodes, and no edge appears twice. - The graph has no cycles, and every node has a directed path to the shipping node. - The answer is at most `10^7`. ### Example 1 ```text Input: nodes = [("m1", "machining", 2), ("m2", "machining", 4), ("i1", "inspection", 1), ("m3", "machining", 3), ("i2", "inspection", 2), ("ship", "shipping", 0)] edges = [("m1", "i1"), ("m2", "i1"), ("i1", "m3"), ("i1", "i2"), ("m3", "ship"), ("i2", "ship"), ("m1", "i2")] Output: 8 ``` The starting nodes are `m1` and `m2`. The longest path is `m2 -> i1 -> m3 -> ship`, with length 4 + 1 + 3 + 0 = 8. The other paths are shorter: `m1 -> i1 -> m3 -> ship` has length 6, `m2 -> i1 -> i2 -> ship` has length 7, `m1 -> i1 -> i2 -> ship` has length 5, and `m1 -> i2 -> ship` has length 4. ### Example 2 ```text Input: nodes = [("x", "machining", 1), ("y", "machining", 1), ("z", "inspection", 1), ("w", "machining", 5), ("ship", "shipping", 1)] edges = [("x", "y"), ("y", "z"), ("z", "ship"), ("w", "ship")] Output: 6 ``` The chain `x -> y -> z -> ship` has more operations but length 4, while `w -> ship` has length 5 + 1 = 6.

Constraints

  • 1 <= len(nodes) <= 10^4
  • 0 <= len(edges) <= 5 * 10^4
  • 0 <= duration <= 1000 for every node.
  • Node ids are unique, nonempty strings of at most 20 characters. Types are nonempty lowercase strings.
  • Exactly one node has type "shipping", and it has no outgoing edges.
  • Every edge connects two different existing nodes, and no edge appears twice.
  • The graph has no cycles, and every node has a directed path to the shipping node.
  • The answer is at most 10^7, so it fits in a signed 32-bit integer.

Examples

Input: ([('ship', 'shipping', 2)], [])

Expected Output: 2

Explanation: Example 3: only the shipping node, so the lead time is its own duration 2.

Input: ([('ship', 'shipping', 0)], [])

Expected Output: 0

Explanation: Minimum valid input with a zero-duration shipping node: the only path has length 0.

Hints

  1. Operations that do not depend on each other run at the same time, so the lead time is set by the slowest chain of dependencies, not by the total of all durations or by how many operations a path has (see Example 2).
  2. A path's length counts node durations, not edges, and it includes both the starting node's duration and the shipping node's duration.
  3. Nothing guarantees that the nodes or the edges are listed in dependency order.

Loading coding console...

Show the approach

Approach

Map every node id to an index, record each node's duration and the index of the node whose type is "shipping", then build outgoing adjacency lists and in-degrees from the edge list. Process the nodes in a topological order with Kahn's algorithm: start from every node with in-degree 0 (exactly the starting nodes). When node u is removed, set finish[u] = duration[u] + best[u], where best[u] is the largest finish value among u's predecessors (0 if u has none); then raise best[v] to finish[u] for every successor v, decrement v's in-degree, and enqueue v when it reaches 0.

Invariant: a node is removed only after all of its predecessors, so best[u] is final when u is removed. By induction over that order, finish[u] is the maximum duration sum over paths that start at a node with no incoming edges and end at u: a node with no predecessors is its own only such path, and every longer path to u is a best path to one predecessor followed by u. Because the graph is acyclic, every backward chain of predecessors ends at a starting node and every node is removed exactly once, so finish[shipping] is exactly the maximum over all starting-node-to-shipping paths, counting both the starting node's and the shipping node's durations.

Edge cases: a work order made of only the shipping node (no edges) returns that node's own duration, which may be 0; zero-duration operations add nothing but still connect paths; node types other than "shipping" and ids that merely look like "ship" are ignored; nodes and edges may arrive in any order because the processing order comes from in-degrees, not list positions. The answer is at most 10^7, so 32-bit integers suffice.

Time complexity:
O(V + E)
Space complexity:
O(V + E)