Problem: A work order is modeled as a DAG. Nodes are operations (machining, inspection, and so on), each with a duration in days, and edges are dependencies. All paths end at a terminal "shipping" node. Compute the total lead time, meaning the critical path length: the longest path from any starting node (no incoming edges) to shipping.
Input was a list of nodes (id, type, duration) and a list of edges (source, target).
Similar to LeetCode's Parallel Courses III.