iTech Robotics and Automation · Software Engineer
Updated · 2026-09-24

iTech Robotics and Automation Software Engineer
Interview Questions & Guide 2026

THE 60-SECOND BRIEF

At iTech Robotics and Automation, the Software Engineer role is the bridge between conceptual industrial automation and high-performance execution. You are not just writing code; you are architecting the logic that drives complex assembly lines, battery manufacturing, and electric vehicle (EV) infrastructure. Your contributions directly affect the efficiency and precision of large-scale robotic systems and support the company's mission to advance automated manufacturing.

Find out what you will be typing into. A shared plain-text editor with no autocomplete, compiler or test runner changes what you have to hold in your head, and practising inside your own configured environment hides exactly that gap.

iTech Robotics and Automation candidates report 4 rounds · ≈ 3-5 weeks. The stages below are what candidates describe, not a published process.

Make every external side effect safe to retryReserve inventory without overselling under concurrent allocationFold late, out-of-order scan events by event time

42 min read

Browse Software Engineer questions

See the practice prompts

16Practice promptsAcross five skill areas
3With worked solutionsIncluded in the practice prompts

At iTech Robotics and Automation, the Software Engineer role is the bridge between conceptual industrial automation and high-performance execution. You are not just writing code; you are architecting the logic that drives complex assembly lines, battery manufacturing, and electric vehicle (EV) infrastructure. Your contributions directly affect the efficiency and precision of large-scale robotic systems and support the company's mission to advance automated manufacturing.

This role requires a unique blend of software proficiency and hardware awareness. You will work within interdisciplinary teams, collaborating with mechanical and controls engineers to solve high-stakes challenges in real-time environments. Whether you are optimizing a PLC program or designing software architectures for battery assembly, the work is intellectually demanding and offers the opportunity to see your code manifest in physical, industrial-scale robotics.

01

Technical Screening

reported

Input bounds are the part of the prompt most often skimmed, and they usually contain the answer. They tell you which complexity class is admissible, which narrows the search before you have thought about the problem itself. As a rough planning figure, a compiled language does on the order of 10^8 simple operations per second and an interpreted one roughly an order of magnitude less. So n up to about twenty admits enumerating subsets, a few thousand admits a quadratic pass, and a million admits neither: you need near-linear, or linear with a log factor. If the bounds are missing, ask for them.

What to demonstrate

  • Whether the approach is justified by the stated input size rather than by whichever pattern you recognised first
  • Whether you ask about the properties that change the algorithm: whether the input arrives sorted, whether duplicates occur, whether values are bounded integers, whether it all fits in memory
  • Whether you can name the bottleneck in your own solution and what would remove it, even when you deliberately leave it in place
  • Whether a claimed speedup is real, since memoising a recursion only helps when subproblems genuinely overlap and the state can be keyed cheaply

How to prepare

  • For each algorithm you rely on, write down the largest n it handles in roughly a second, then check two of those figures by timing them in the language you will actually type in
  • For two weeks, write one line naming your target complexity and the bound that justifies it before you write any code, then compare that line with what you ended up submitting
  • Practise the conversion backwards: given a required O(n log n), list the mechanisms that get you there (sorting, a heap, an ordered map, divide and conquer) and choose by what the problem needs to query, not by what you used last
PracHub interview research ↗
02

System Design Interview

reported

An unlabelled round is first an information problem, and the cheapest information is free. Whoever schedules it can usually tell you how long it runs, who will be in the room and what they work on, whether you will be writing code and in what environment, and whether anything is being sent beforehand. Ask in writing so the answer is on record, then prepare for the two or three formats those answers still leave open instead of betting on one. What separates a strong candidate is not guessing right; it is having an opening that works whichever one it turns out to be.

What to demonstrate

  • Whether you can start work from an ambiguous brief, since tolerating a vague scope without stalling is the same thing the job asks for
  • Whether the questions you asked beforehand were ones that change your preparation, such as duration, medium and who is joining, rather than ones whose answers you could not have acted on
  • Whether you adapt when the round turns out to be something other than what you were told, instead of spending the first ten minutes visibly recalibrating

How to prepare

  • Send one short scheduling message asking four things: how long, who is joining and what they work on, whether you will be writing code and where, and whether to prepare anything in advance. Treat a vague reply as real information, since it means the round is loosely structured and you will be shaping it yourself.
  • Write one opening that works in any of the formats still open: restate in your own words what you have been asked to do, then ask which of two directions is more useful to them. Say it aloud until it stops sounding recited.
  • Set up for the two most likely formats before the call starts, with a blank editor in the language you would choose and a shared document you can type into, so a format surprise costs you nothing in the first minutes
PracHub interview research ↗
03

Past Project Experiences

reported

You cannot drill a format you do not know, so put the preparation into material that travels. Three pieces of your own work, each rehearsed until you can take a follow-up you did not anticipate, will carry a conversation or a code walkthrough equally well. Specificity is what separates that from filler. A number needs its definition before it means anything: a p99 is over some window and measured at some hop, and a server-side figure excludes the queueing and network time a client would see. The number you cannot qualify is the one to leave out.

What to demonstrate

  • Whether your examples carry detail only someone who did the work would hold, such as what the binding constraint actually was, which alternative you rejected and why it was worse, and what you measured on each side of the change
  • Whether a number survives one follow-up, meaning you can say what it was measured over and whether it moved because of your change or merely alongside it
  • Whether a failure is described with the specific change that followed it, rather than a lesson stated in general terms
  • Whether your part in a team effort is stated accurately, including what other people did

How to prepare

  • Write a page on each of three projects covering the constraint, the option you rejected, the measurement before and after, and what went wrong. Cut any line you cannot take a follow-up on, since you are writing the parts you will be pressed on rather than a summary.
  • Recover the real figures while you still have access: request volume, data size, latency with its percentile and window, team size, timeline. Note where each came from, whether a dashboard, a design document or memory, and mark the estimates so you can say which they are out loud.
  • Take your weakest project story to someone who works in a different area and have them ask why four times in succession. The point where you run out of answer is the part to go and re-read before the round.
PracHub interview research ↗
04

Culture Alignment

reported

This round is deciding whether a change you make without supervision can be allowed to reach production. It is scored on what you knew at the moment you decided, not on how it turned out, so a story that opens with the result and works backwards reads as luck retold as judgement. Say what the options were, what you did not know, what you did to shrink the unknown before committing, and what you accepted as the worst plausible case. The detail that separates answers is a bound: how many users, how much data, and for how long, if you had been wrong.

What to demonstrate

  • Whether the reasoning you give was available at the time you decided rather than after the result came in, since a story whose deciding evidence arrived later describes an outcome and not a judgement
  • Whether you can put units on the exposure (users, rows, minutes of degraded service) and whether the containment you chose actually bounded it: a canary bounds the request path it fronts, while a background job writing to a shared table reaches every user regardless of which version served their requests
  • Whether the reversal path existed before you shipped or was improvised during the incident, and whether it restores state or only stops further damage

How to prepare

  • For your three largest changes, write down the one thing you would have had to be wrong about for it to fail, and what your best estimate of it was on the day you shipped. If you never held an estimate, that is the gap the follow-up questions will find
  • Write the undo procedure for one of those changes as it existed at the time, then mark which steps restore data and which only stop new damage. Turning a flag off or reverting a deploy ends the new writes; rows already written come back only from a copy you kept, and a dropped column comes back empty unless something outside the schema holds the values
  • Rehearse one story from the decision point forward and stop before the outcome, then have someone ask what you would do next. If the story only works with the ending attached, it is an anecdote rather than a decision you can defend
PracHub interview research ↗

PracHub editorial advice for the preparation topics above.

01

Floating-point quantities and implicit unit-of-measure conversions

Binary floating point cannot represent most decimal fractions exactly, so a chain of pallet-to-case-to-each conversions accumulates a residue that a later rounding turns into a unit that was created or destroyed, breaking conservation with no concurrency involved at all. The bug is slow and non-local: it surfaces as a cycle-count variance weeks later, at a node nobody changed, and it is untraceable because the arithmetic looked correct at every individual step. The fix is to hold quantities as integers in the smallest transacting unit, carry the UoM explicitly on every row that carries a number, store conversion factors as integers that are versioned in time, and reject a conversion that does not divide exactly instead of rounding it. The same discipline applies to money on the freight side, where an accessorial in floating-point dollars produces invoice reconciliation differences of a cent that cost more to investigate than the freight.

02

Holding a database transaction open across a physical or third-party operation

It is natural to open a transaction, lock the position, call the rating or tendering API, and commit on the response, and it works perfectly until the partner's p99 goes from 200 milliseconds to thirty seconds. At that point every request holding a lock on a hot item-node pair queues behind it, the connection pool fills with transactions that are waiting on the network rather than on the database, and an unrelated service sharing the pool fails at the same moment. In this domain the effect is amplified because demand concentrates on a few hot rows during a promotion or a seasonal peak, exactly when partner latency is also degraded. The structural fix is to keep transactions short and local - commit the state change together with an outbox row, let a relay perform the external call, and reconcile asynchronously - accepting at-least-once delivery and making the effect idempotent rather than trying to stretch a transaction over something the database cannot roll back.

03

Assuming fixed-width integer arithmetic cannot overflow

In languages with fixed-width integers, including C, C++, Java, Go and Rust, computing a midpoint as (lo + hi) / 2 overflows once the sum passes the type's maximum, so write lo + (hi - lo) / 2 instead. Say which language you are in: arbitrary-precision integers, as in Python or Ruby, remove this specific hazard and none of the others.

04

Reading the constraints as preamble rather than as part of the problem

The bounds are usually there to eliminate the obvious approach: n up to 10^5 makes an O(n^2) scan roughly 10^10 operations, far outside any per-test time budget, and an input larger than memory rules out loading it at all. When a bound is not given, ask for it, then say out loud which approach it kills.

Choose a category, try a prompt, then open its approach, worked solution or follow-up when you need it.

13 technical prompts3 include a worked solution

Trace a suspect lot forward to every shipped order line

mediumWorked solution
graph traversalgenealogyindexing

lot_edge(parent_lot_id, child_lot_id) has 400 million rows with btree indexes on both (parent_lot_id, child_lot_id) and (child_lot_id, parent_lot_id). lot_shipment(lot_id, order_line_id) maps lots to shipped lines. Given one suspect received lot, return every downstream order_line_id. The reachable subgraph can reach 2 million lots and 12 levels; the full edge table does not fit in memory. Give the traversal, its complexity in terms of the reachable subgraph, and what you do if the data contains a cycle.

Approach
  1. Genealogy is a directed acyclic graph, not a tree: a production run consumes several lots and one lot splits across many shipments, so a node is reached by several paths and a tree traversal revisits it combinatorially. Breadth-first from the suspect lot over the (parent_lot_id, ...) index, with a hash set of visited lot ids, is O(V' + E') where V' and E' count only the reachable subgraph — 2 million 8-byte ids is 16 MB of payload and a few tens of MB with open-addressing overhead, which is why the visited set is affordable and the edge table's 400 million rows never enter memory.
  2. Batch each level into one indexed read. Issue WHERE parent_lot_id = ANY($1) with a few thousand parents per call instead of a query per node: at 12 levels and 2 million nodes, per-node round trips dominate the wall clock entirely, and the recall's deadline is a real-world response time, not a query-plan aesthetic. The batch size is the tuning knob between round-trip count and per-statement planning cost.
  3. Keep the visited set even though the schema says DAG. Rework and repack loops — material returned into an earlier lot — do occur, and an unguarded traversal on a cyclic edge set does not terminate; a set membership test is O(1) and turns a hang into a correct answer plus a data-quality alert. Also cap the traversal by level and by node count, and fail loudly on the cap rather than returning a partial set silently.
  4. Join to lot_shipment once at the end over every visited lot id, not over the leaves and not per node. A lot is routinely both shipped and consumed: half a lot goes out on an order line while the other half is repacked into a child lot, so it has a lot_shipment row and outgoing edges at the same time and is not a leaf. Restricting the join to nodes with no outgoing edges drops exactly those order lines, which is under-recall — the one failure mode this trace is not allowed to have. One bulk join against an index on lot_id over the whole visited set is a single pass; per-node lookups multiply the round-trip problem by the number of visited lots.
  5. State the semantics honestly: reachability answers which shipped lines could contain material from the suspect lot, and without propagating edge quantities it is a superset of physical containment. For a recall that is the correct direction of error — over-recall, never under-recall — and saying so is the point, because a trace that returns quickly and incompletely will be believed. The upstream question, which received lots are in a suspect shipped unit, is the same traversal over the reverse index, which is why both indexes exist.
Worked solution 30 min
  1. Draw a six-lot fixture containing a merge (two parents into one child), a split (one parent into three children), and one interior lot that is partly shipped on an order line and partly consumed into a child lot, then write down the expected reachable set and the expected order lines by hand.
  2. Implement level-batched BFS with an explicit frontier list, a visited hash set, and a per-level batch read.
  3. Add a cycle to the fixture and confirm the traversal terminates and flags it rather than hanging.
  4. Bulk-join lot_shipment once over every visited lot id — the whole visited set, not the leaves — and count the queries issued, confirming it is one per level plus one.
  5. Re-run with the frontier order reversed to confirm the output set is unchanged.
EXPECTED RESULTEvery lot downstream of the suspect appears exactly once in the visited set; the merge node is visited once, not twice; the partly-shipped interior lot contributes its order line even though it has children; the cyclic fixture terminates with the same reachable set plus a flagged edge; the query count is levels + 1, not proportional to node count.
Follow-up
  • A recursive CTE would express this in ten lines. What is its cost here if the index on the traversal column is missing, and how would you notice?
  • You need the quantity of suspect material in each downstream line, not just reachability. What has to be on the edge, and what does that do to the traversal?
  • The traversal must run while a production run is writing new edges. What does a consistent answer mean here, and what do you cut it at?

Fold late out-of-order status events into a monotonic leg state

hard
semilattice foldevent timeidempotency

Leg statuses form the chain planned < tendered < accepted < picked_up < in_transit < delivered, with exception and cancelled outside it. You ingest 300 million observation_event rows a day carrying subject_id (leg), observed_status, occurred_at, received_at, clock_offset_ms and dedupe_key; five percent arrive over an hour late and a tail arrives a day late. Write the merge that produces each leg's current status, prove the result depends only on the set of events and not their order, and state the per-event cost.

Approach
  1. Define the per-leg state as a tuple ordered totally: (status_rank, occurred_at, source_priority, event_id), and define merge(a, b) as the maximum under that order. Rank leads; occurred_at and the rest only break ties. The proof is then one line: maximum over a total order is idempotent, commutative and associative, so the state space with merge is a join-semilattice and the fold over any permutation of the event set yields the same value. That is also why no global sort is needed — the O(n log n) disappears and the fold is O(1) per event, O(distinct legs) state.
  2. Rank before time, deliberately. occurred_at is device-reported and sometimes wrong; if it led the comparison, the leg's status would be handed to whichever device has the most badly skewed clock. Ranking first means a bad clock can only reorder events within one rank. Correct occurred_at by clock_offset_ms where it was measured, and where the offset exceeds a threshold keep the observation but bar it from winning a tie — the event is still evidence, it just stops being authority.
  3. Make the lattice total, because exception and cancelled are not points on the chain and max over a partial order is undefined for incomparable pairs. Model cancelled as an absorbing top element, and carry exception as a boolean flag merged by OR alongside the rank rather than as a rank of its own — otherwise an exception at rank 4 either blocks delivered at rank 6 or is erased by it, and both are wrong. A product of semilattices is a semilattice, so the order-insensitivity argument still holds over the tuple.
  4. Deduplicate on dedupe_key even though the merge is idempotent. Idempotence covers a byte-identical redelivery; a partner replaying a window with a fresh event_id is not identical, and the tie-break would let the replay displace the original for no reason. Dedupe on the stable key, then fold — both halves are needed, and conflating them is the usual defect.
  5. Partition the stream by subject_id so all events for one leg land on one partition: broker ordering guarantees are per-partition only, and while a commutative merge makes interleaving harmless, a concurrent read-modify-write on the same leg row is still a lost update. Where that cannot be guaranteed, make the write a compare-and-set on a version column, or a conditional update that only raises the state. Because the state is mergeable, shard maps combine cleanly and replaying the whole day converges to the same answer — which is what makes reprocessing safe.
  6. Say where genuine regressions live: a delivered shipment that is refused and returns is a new leg, not a rank decrease. Monotonicity is only sound if real reversals are modelled as new objects, and keeping every superseded observation is what lets you answer the dispute later, so the fold discards nothing — it marks losers superseded.
Follow-up
  • An event arrives a week late for a leg already closed and invoiced. Does it change the status, the on-time metric, both, or neither?
  • Two events for one leg have the same rank and the same occurred_at from different sources. What decides, and is that decision stable across a replay?
  • How would you test order-insensitivity rather than assert it?

Find the hottest write keys under a fixed memory budget

medium
top-kheapstreaming sketches

One day of writes to inventory_movement is 200 million rows; each carries (item_id, node_id). Distinct pairs reach 60 million. Return the 200 pairs with the most writes so they can be moved behind a single writer before the next peak. First give the exact answer assuming you may hold 60 million counters, then give an answer under a 200 MB budget, and state the error guarantee that second answer carries. Both must be one pass over the day's rows unless you argue for a second.

Approach
  1. Exact version: one hash pass to build (item_id, node_id) -> int64, then a single scan of the map maintaining a min-heap of size K = 200, pushing and popping when the incoming count exceeds the heap root. O(n + d log K) with n = 2e8 and d = 6e7, versus O(d log d) if you sort all 60 million entries — a factor of roughly log d / log K, about 3.4x, for no benefit. The heap must be a min-heap: the root is the weakest survivor, so eviction is O(log K).
  2. Cost the map honestly. 60 million entries at a 16-byte key, an int64 count and per-entry overhead is 2-3 GB in most runtimes, which is the whole reason for the second version rather than a theoretical aside.
  3. Bounded version: Misra-Gries with m counters. Keep at most m keys with counts; on a key already present increment it; on a new key when fewer than m are held, insert at 1; otherwise decrement every held counter and drop those reaching zero. With m = 1,000,000 at roughly 40 bytes per counter, that is about 40 MB, comfortably inside 200 MB alongside the heap.
  4. State the guarantee as a number, not as 'approximate'. Misra-Gries returns an estimate satisfying f - n/(m+1) <= f_hat <= f, so with n = 2e8 and m = 1e6 every count is an undercount by at most 200. If the 200th hottest pair has hundreds of thousands of writes, a 200-count error cannot reorder the top of the list — and if the counts near rank 200 are within 200 of each other, the ranking there was never meaningful for the decision being made. The sketch also merges: run one per shard, combine, prune back to m, and the bound holds with n the combined length.
  5. If exactness is genuinely required, argue for two passes rather than more memory: the Misra-Gries pass yields a candidate superset of size m, and a second pass counts only those candidates exactly in O(m) memory. That is the standard way to get an exact top-K under a memory bound, and the cost is one extra read of the day's rows.
Follow-up
  • The decision downstream is which keys get a single writer. Does a rank error at position 190 change that decision, and what does the answer tell you about how much accuracy to buy?
  • Write volume on one key is bursty — a promotion concentrates it into twenty minutes. Does a daily top-K find it, and what window would?
  • How do you keep the sketch across a worker restart without replaying the day?

Four days sample coding, design, fundamentals and the practical rounds at deliberately shallow depth, which is enough to surface the topics you did not know were in scope. That map, rather than a guess made on day one, decides where the last three days go.

Small steps. Visible outcomes.0 / 7 completed
ONE WEEK · YOUR PACE

Prepare, practise & reflect

One practical outcome each day. Spend longer where you need it.

0 / 7 done
01Coding, one pass at shallow depth
  • Solve one problem from each of six families, an array with two pointers, hash counting, binary search, a tree traversal, a graph traversal and one dynamic program, under a hard twenty-minute cap with no extensions, marking each finished, late, or stalled.
  • For every stall, write the exact move you could not make rather than the subject, so the note reads could not turn the recurrence into a loop rather than bad at dynamic programming.
  • Fix nothing today. The value of the pass is the unfixed record.

Deliverable: Six timed attempts marked finished, late or stalled, each stall carrying a named blocking move.

Practice prompt ↗Practice prompt ↗Practice prompt ↗Worked solution ↗
02Design, one pass at shallow depth
  • Spend twenty minutes each on three different shapes, a read-heavy feed, a write-heavy ingest path, and something needing a transaction across two entities, stopping each at requirements, interface and data model.
  • After each, write the first question you could not answer, which is usually a number you could not estimate or a failure mode you had no vocabulary for.
  • Mark which of the three you would be most relieved not to be asked, and treat that as data rather than as a preference.

Deliverable: Three shallow designs, each with the first unanswerable question written at the bottom.

Practice prompt ↗Practice prompt ↗Practice prompt ↗
03Fundamentals and the practical rounds
  • Answer eight short questions in writing at four minutes each, covering the material that fills the gaps between the big rounds: what happens between a URL and a rendered page, what an index costs on write, when a process is preferable to a thread, and what conditions a deadlock requires.
  • Do one thirty-minute practical task of the kind a take-home compresses: read an unfamiliar two-hundred-line file and write what it does, what you would change, and the one thing you remain unsure of.
  • Score every answer fluent, correct but slow, or absent, and keep the absent ones visible.

Deliverable: Eight scored short answers and one written reading of unfamiliar code.

Practice prompt ↗Practice prompt ↗
04The rounds that are about you, and the map
  • Deliver three behavioural answers aloud against a timer, a conflict, a failure you owned, and a decision made without enough information, marking any that ran past three minutes or contained no number.
  • Assemble the map: every marked item from days one to three on a single page, sorted by how likely it is to appear in your loop rather than by how uncomfortable it felt.
  • Choose exactly two areas for the remaining three days and write down what you are deliberately abandoning.

Deliverable: A one-page scored map of the whole surface area with two areas chosen and the rest explicitly abandoned.

Practice prompt ↗Practice prompt ↗Worked solution ↗
05First chosen area, to the depth you skipped
  • Work the higher-ranked area in four focused blocks, choosing items one level above where you stalled rather than repeating what already works.
  • After each block write the rule you extracted in one sentence with its precondition attached, since a rule carrying no precondition is exactly what fails under a variation.
  • Re-attempt the day-one or day-two item that exposed this area and compare against the original timing.

Deliverable: Four worked blocks, a timed re-attempt against the original, and three one-sentence rules with preconditions.

Practice prompt ↗Practice prompt ↗
06Second chosen area, where the gap is coverage rather than speed
  • Treat the second area differently from the first. Day five drilled something you could already half-do; this one is usually a topic you had simply never met, so build one worked reference example end to end and keep it, rather than attempting six problems badly.
  • Write down the vocabulary you were missing on day two or three, five terms at most, each with the one sentence that makes it usable in an answer rather than the textbook definition.
  • Redo the shallow attempt that exposed this area and note whether you now fail later in the problem, because moving the failure point is the realistic gain from a single day and is worth more than a score that did not change.

Deliverable: One worked reference example for the newly covered area, a five-term vocabulary list, and a note on where the failure point moved.

Practice prompt ↗Practice prompt ↗
07Reassemble the loop
  • Sit two rounds back to back with no gap, ordering them so the area you chose second comes last, because the map was built from rested, isolated attempts and the loop will reach your weaker area when you are already spent.
  • Write where the second round suffered from the first, which is normally the point at which structure collapses into narration.
  • Reduce the week to one page holding only the rules you can state without reading them.

Deliverable: Mock notes on cross-round carryover plus a one-page card of rules you can recite from memory.

Practice prompt ↗Practice prompt ↗Worked solution ↗

Expand any day for tasks and deliverables. Your progress is saved on this device.

A migration is a cost you chose to pay, not an achievement. The story is what the old system made expensive, what you measured before committing, what kept serving traffic during the cutover, and what you would have done if the numbers had come back flat. Without those, a rewrite reads as taste.

Describe a situation where you encountered a critical system failure; …

medium
behavioural and engineering judgement

Describe a situation where you encountered a critical system failure; how did you identify the root cause?

Approach
  1. Name the disagreement and how you resolved it with evidence.
  2. Give the blast radius: what could have broken, and what you measured.
  3. State the situation in two sentences and spend the rest on the reasoning.
Follow-up
  • What did you decide not to do, and why?
  • What would you do differently if you ran that again?

How do you handle competing project priorities in a fast-paced enginee…

medium
behavioural and engineering judgement

How do you handle competing project priorities in a fast-paced engineering environment?

Approach
  1. Close with what you would do differently, concretely.
  2. Name the disagreement and how you resolved it with evidence.
  3. Pick a story where you made the decision, not one where you watched it.
Follow-up
  • How did you know your change caused the improvement?
  • What would you do differently if you ran that again?

Resolve a review disagreement over clamping a position

easy
code reviewinvariantsreconciliationdisagreement

A pull request changes the pick path from a plain decrement to qty = GREATEST(qty - :n, 0) on inventory_position, because the CHECK (qty >= 0) constraint has been failing a few times a day and paging the on-call. The author argues the page is noise and a negative on-hand is meaningless anyway. You disagree. Describe a code review disagreement you had: the argument you made, how you kept it about the system rather than the person, what you conceded, and how it ended. State what the clamp destroys and what you proposed be done with the failures instead.

Approach
  1. Name the information the clamp destroys, in one sentence: the constraint failure is the only signal that the ledger and the shelf disagree, and GREATEST turns a detectable variance into a silent one that surfaces later as a picker standing at an empty location for an order the system promised.
  2. Concede the real half of the author's case immediately, because it is real: paging a human on a data condition that a human cannot fix at 3am is bad design. The disagreement is not whether the page should stop but whether stopping the page should also stop the evidence.
  3. Propose the version that satisfies both: catch the constraint violation at the application boundary, write a cycle_count_adjust movement with its own reason code and reference so the correction is a first-class row rather than an invisible edit, fail the pick task with a specific error the floor can act on, and move the alert from a page to a variance report per item-node pair.
  4. Anchor the argument in the append-only model rather than in taste. Positions are derived from inventory_movement, so a clamp makes the position stop equalling the sum of its movements and the reconciliation job now reports a permanent, unexplainable variance on that key.
  5. Say how you handled the disagreement mechanically: the comment thread, then a short synchronous conversation once it became clear the thread was circling, and a written decision so the next person reading the clamp knows why it is not there.
  6. State the concession you actually made, including if you lost. Losing a review and writing the detector anyway is a legitimate and common outcome worth describing plainly.
Follow-up
  • The clamp has already been in production for a month. How do you find out how much stock it silently absorbed?
  • Where should the adjustment movement get its reference, given that no count sheet exists at pick time?
  • The author is more senior than you and unconvinced. What is your next move?
  • 01

    Describe a situation where you encountered a critical system failure; how did you identify the root cause?

  • 02

    How do you handle competing project priorities in a fast-paced engineering environment?

  • 03

    A pull request changes the pick path from a plain decrement to qty = GREATEST(qty - :n, 0) on inventory_position, because the CHECK (qty >= 0) constraint has been failing a few times a day and paging the on-call. The author argues the page is noise and a negative on-hand is meaningless anyway. You disagree. Describe a code review disagreement you had: the argument you made, how you kept it about the system rather than the person, what you conceded, and how it ended. State what the clamp destroys and what you proposed be done with the failures instead.

PracHub interview preparation framework ↗
Is this an official iTech Robotics and Automation interview guide?

No. It is PracHub's own research and practice material for the Software Engineer role at iTech Robotics and Automation. Rounds and questions reflect what candidates have reported, not a process iTech Robotics and Automation has published, and they change over time. Confirm the current format and scope with your recruiter.

PracHub interview research ↗
How difficult are the technical interviews?

The interviews are designed to be challenging but fair. They focus on practical, real-world scenarios rather than abstract puzzles, so focus on your hands-on experience and problem-solving process.

PracHub interview research ↗
What is the typical timeline for the hiring process?

While it can vary based on business needs, the process typically moves from the initial screen to a final decision within 3–5 weeks. Candidates report that the process is kept efficient.

PracHub interview research ↗
How much preparation time do you recommend?

Plan for at least 1–2 weeks of focused preparation, specifically reviewing your past projects and refreshing your knowledge of the core technical domains relevant to the position.

PracHub interview research ↗
What differentiates a successful candidate?

Successful candidates demonstrate a blend of technical mastery and a pragmatic, collaborative mindset. Being able to explain "why" you made a design choice is often more important than the specific tool you used.