Find the critical path and its total time in a service dependency DAG

Quick Overview

Given services with execution times and dependency edges that form a DAG, return the total time of the longest source-to-sink path and the services along it, breaking ties by the lexicographically smallest path. It tests topological ordering, dynamic programming on a DAG and path reconstruction.

Find the critical path and its total time in a service dependency DAG

Company: Discord

Role: Software Engineer

Category: Coding & Algorithms

Difficulty: medium

Interview Round: Other

You are given `n` services labeled from `0` to `n - 1`, a list of directed dependency `edges` where `edges[i] = [u, v]` means service `u` must complete before service `v` can start, and an array `times` where `times[i]` is the execution time of service `i`. The services form a directed acyclic graph (DAG). The **critical path** is the longest path (by total execution time) from any source service (a service with no dependencies) to any sink service (a service with no dependents). This path determines the minimum total time to complete all services when independent services can run at the same time. Return an array where the first element is the total latency of the critical path, followed by the ordered list of service indices along that path. ### Function Signature ```python def critical_path(n: int, edges: list[list[int]], times: list[int]) -> list[int]: ``` ### Rules - An edge `[u, v]` points from `u` to `v`, and `u` runs first. - The total time of a path is the sum of `times[i]` over every service on it, including the first and the last. Edges add no time of their own. - A service with no edges at all is both a source and a sink, so on its own it forms a path of one service. - When several critical paths have the same total time, return the one whose index sequence is lexicographically smallest: compare the sequences element by element, and the first position where they differ decides in favor of the smaller index. ### Constraints - `1 <= n <= 10^4` - `0 <= len(edges) <= 5 * 10^4` - `0 <= edges[i][0], edges[i][1] < n` - `1 <= times[i] <= 10^4` - The graph is a valid DAG (no cycles). ### Examples ```text Input: n = 6, edges = [[0, 2], [1, 2], [2, 3], [2, 4], [3, 5], [4, 5]], times = [3, 2, 5, 4, 6, 2] Output: [16, 0, 2, 4, 5] ``` The critical path is `0 -> 2 -> 4 -> 5` with total latency 3 + 5 + 6 + 2 = 16. The other paths are shorter: `1 -> 2 -> 4 -> 5` totals 15 and `0 -> 2 -> 3 -> 5` totals 14. ```text Input: n = 4, edges = [[0, 1], [0, 2], [1, 3], [2, 3]], times = [1, 10, 2, 3] Output: [14, 0, 1, 3] ``` The critical path is `0 -> 1 -> 3` with total latency 1 + 10 + 3 = 14. The branch through service 2 totals only 1 + 2 + 3 = 6. ```text Input: n = 5, edges = [[0, 1], [0, 2], [1, 3], [2, 3], [4, 3]], times = [1, 3, 3, 2, 4] Output: [6, 0, 1, 3] ``` All three source-to-sink paths, `0 -> 1 -> 3`, `0 -> 2 -> 3` and `4 -> 3`, total 6. The tie rule picks `[0, 1, 3]`: it starts with the smallest index, and at the second position 1 is smaller than 2.

Overview: Given services with execution times and dependency edges that form a DAG, return the total time of the longest source-to-sink path and the services along it, breaking ties by the lexicographically smallest path. It tests topological ordering, dynamic programming on a DAG and path reconstruction.

Discord logo
Discord
Nov 24, 2026
mediumSoftware EngineerOtherCoding & Algorithms
0
0

You are given n services labeled from 0 to n - 1, a list of directed dependency edges where edges[i] = [u, v] means service u must complete before service v can start, and an array times where times[i] is the execution time of service i.

The services form a directed acyclic graph (DAG). The critical path is the longest path (by total execution time) from any source service (a service with no dependencies) to any sink service (a service with no dependents). This path determines the minimum total time to complete all services when independent services can run at the same time.

Return an array where the first element is the total latency of the critical path, followed by the ordered list of service indices along that path.

Function Signature

def critical_path(n: int, edges: list[list[int]], times: list[int]) -> list[int]:

Rules

  • An edge [u, v] points from u to v , and u runs first.
  • The total time of a path is the sum of times[i] over every service on it, including the first and the last. Edges add no time of their own.
  • A service with no edges at all is both a source and a sink, so on its own it forms a path of one service.
  • When several critical paths have the same total time, return the one whose index sequence is lexicographically smallest: compare the sequences element by element, and the first position where they differ decides in favor of the smaller index.

Constraints

  • 1 <= n <= 10^4
  • 0 <= len(edges) <= 5 * 10^4
  • 0 <= edges[i][0], edges[i][1] < n
  • 1 <= times[i] <= 10^4
  • The graph is a valid DAG (no cycles).

Examples

Input: n = 6, edges = [[0, 2], [1, 2], [2, 3], [2, 4], [3, 5], [4, 5]], times = [3, 2, 5, 4, 6, 2]
Output: [16, 0, 2, 4, 5]

The critical path is 0 -> 2 -> 4 -> 5 with total latency 3 + 5 + 6 + 2 = 16. The other paths are shorter: 1 -> 2 -> 4 -> 5 totals 15 and 0 -> 2 -> 3 -> 5 totals 14.

Input: n = 4, edges = [[0, 1], [0, 2], [1, 3], [2, 3]], times = [1, 10, 2, 3]
Output: [14, 0, 1, 3]

The critical path is 0 -> 1 -> 3 with total latency 1 + 10 + 3 = 14. The branch through service 2 totals only 1 + 2 + 3 = 6.

Input: n = 5, edges = [[0, 1], [0, 2], [1, 3], [2, 3], [4, 3]], times = [1, 3, 3, 2, 4]
Output: [6, 0, 1, 3]

All three source-to-sink paths, 0 -> 1 -> 3, 0 -> 2 -> 3 and 4 -> 3, total 6. The tie rule picks [0, 1, 3]: it starts with the smallest index, and at the second position 1 is smaller than 2.